Skip to main content

Nuclear Waste Cleanup: Army Corps Could Benefit from Following Leading Practices for Program Management for Contaminated Sites

GAO-23-105968 Published: Sep 19, 2023. Publicly Released: Oct 17, 2023.
Jump To:

Fast Facts

Decades of nuclear energy research and weapons development created radioactive waste at sites in the Midwest and Northeast U.S.—leading to environmental risks for nearby communities.

The U.S. Army Corps of Engineers is cleaning up 19 sites at an estimated cost of $2.6 billion. But the Corps isn't using opportunities to manage this work in a coordinated centralized way. The Corps could use its resources more efficiently if it followed leading program management practices, such as identifying shared staffing needs across projects. We recommended it do so.

The growing cost of cleaning up contaminated sites is on our High Risk List.

U.S. Army Corps of Engineers contractors remove contaminated soil in Tonawanda, New York, in 2019

worker in a digger removing soil from a large pit in the ground while another worker looks on

Skip to Highlights

Highlights

What GAO Found

The U.S. Army Corps of Engineers (Corps) reported $2.6 billion in environmental liabilities in fiscal year 2022 for the estimated future costs to investigate and clean up contamination under its Formerly Utilized Sites Remedial Action Program (FUSRAP). Of the 19 active sites in the program, four sites with complicated cleanup remedies or large amounts of contamination make up about three-quarters of this estimate. However, Corps officials said that FUSRAP's environmental liability has the potential to be affected by uncertainties, such as the discovery of additional contamination after completing a cost estimate for remediation. Since 2016, FUSRAP's environmental liability has risen by nearly $1 billion, an increase that officials attribute to uncertainties, along with inflation.

Formerly Utilized Sites Remedial Action Program Sites in St. Louis, Missouri, and Lockport, New York, Being Cleaned up by the U.S. Army Corps of Engineers

Formerly Utilized Sites Remedial Action Program Sites in St. Louis, Missouri, and Lockport, New York, Being Cleaned up by the U.S. Army Corps of Engineers

GAO's review of FUSRAP documents found that the Corps minimally met selected leading practices for program management related to risk management and cost estimating, among other things. For example:

  • Programs should identify risks and opportunities, document their characteristics, and prepare to manage them. The Corps does not have a documented program-level risk management process for FUSRAP. A program-level risk management process could help officials identify and manage risks that can affect multiple projects, such as limited staffing in areas like procurement, which officials said can extend some projects' timelines.
  • Programs should have an integrated life cycle cost estimate that is comprehensive. Corps officials said that they consider FUSRAP's environmental liability estimate to be the program's life cycle cost estimate. However, the environmental liability estimate does not include all costs and does not track costs from previous years. Having an integrated life cycle cost estimate that includes all program costs could enhance FUSRAP management's ability to make risk-informed decisions on how to manage and allocate its resources.

Corps officials said that the agency's standard business practices do not require FUSRAP to adhere to some of the leading practices at the program level. Although not required, following these and other leading practices would better position the Corps to oversee and manage FUSRAP.

Why GAO Did This Study

Atomic energy activities supported by the federal government generated large amounts of radioactive and hazardous waste over several decades of nuclear weapons production and energy research following World War II. This waste has contaminated soil, groundwater, and structures at sites across the country, posing potential risks to human health and the environment. The Corps is responsible for cleaning up or controlling contamination at some of these sites through FUSRAP.

GAO was asked to provide information about the Corps' efforts to clean up contamination under FUSRAP. This report, among other things, (1) describes the reported environmental liabilities associated with active FUSRAP sites and uncertainties around those estimates and (2) examines the extent to which FUSRAP meets leading practices for program management.

GAO reviewed legal requirements, federal accounting standards, agency documents, and leading program management practices; analyzed data on the Corps' cleanup expenditures and total cost estimates; and interviewed agency officials.

Recommendations

GAO is making five recommendations, including that the Corps conduct risk management and develop a life cycle cost estimate for FUSRAP in accordance with leading program management practices. The Corps agreed with our recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of the Army 1. The Secretary of the Army should ensure that the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers update the FUSRAP Program Management Plan to follow leading practices for program management, for example, by including details in the plan on how to allocate staffing resources shared among project sites. (Recommendation 1)
Open
As of December 2023, the Department of Defense (DoD) plans to update the FUSRAP program management plan for contracting and resourcing needs using leading practices to support program execution by March 31, 2025.
Department of the Army 2. The Secretary of the Army should ensure that the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers create a program roadmap for FUSRAP that follows leading practices for program management, for example, by tracking CERCLA phases for each site and projecting when sites would need contracting support or technical expertise. (Recommendation 2)
Open
As of December 2023, DoD plans to create a roadmap for FUSRAP showing CERCLA phase status for each site using leading program management practices by June 30, 2024.
Department of the Army 3. The Secretary of the Army should ensure that the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers develop a comprehensive, integrated life cycle cost estimate for FUSRAP that follows leading practices for program management, for example, by including both past and future program costs. (Recommendation 3)
Open
As of December 2023, DoD plans to develop a comprehensive, integrated lifecycle cost estimate for FUSRAP that will be updated on a periodic basis by September 30, 2024.
Department of the Army 4. The Secretary of the Army should ensure that the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers conduct risk management for FUSRAP at the program level that follows leading practices for program management, for example, by developing a risk register. (Recommendation 4)
Open
As of December 2023, DoD plans to develop a program level risk register and conduct annual risk management for FUSRAP at the program level by December 30, 2024.
Department of the Army 5. The Secretary of the Army should ensure that the Chief of Engineers and Commanding General of the U.S. Army Corps of Engineers include the specific needs of FUSRAP communities in district level outreach strategies being developed in support of the Justice40 Initiative. (Recommendation 5)
Open
As of December 2023, DoD plans to conduct assessments of district level outreach needs, recommendations and strategies by September 30, 2024. Additionally, DoD plans to update site level community involvement plans and environmental justice strategic plans to include Justice40 goals by December 30, 2024.

Full Report

Office of Public Affairs

Topics

Best practicesCommunitiesCost estimatesEnvironmental liabilitiesGroundwater contaminationHazardous waste site remediationLife cycle costsNuclear waste cleanupProgram managementProject managementRisk management