Hanford Waste Treatment Plant: DOE Is Pursuing Pretreatment Alternatives, but Its Strategy Is Unclear While Costs Continue to Rise

GAO-20-363 Published: May 12, 2020. Publicly Released: May 12, 2020.
Jump To:

Fast Facts

The Department of Energy has been building a nuclear waste treatment plant at its Hanford, Washington site since 2000.

Part of the plant (a pretreatment facility) has cost $3.8 billion so far. Technical challenges that posed major safety risks prompted DOE to stop work on the facility in 2012. Since then, DOE has spent $752 million (as of FY 2018), mostly to preserve and maintain it, and another $400 million pursuing facility alternatives to try to meet a 2023 goal. DOE has not used the best available methods to determine which alternative to pursue.

We made 2 recommendations, including that DOE follow best practices to select an alternative.

The Partially Constructed Hanford Pretreatment Facility in Washington State, 2013 and 2020

Side-by-side photos of a building under construction in 2013 and 2020

Side-by-side photos of a building under construction in 2013 and 2020

Skip to Highlights

Highlights

What GAO Found

The Department of Energy's (DOE) Office of Environmental Management (EM) spent $752 million in fiscal years 2013 through 2018 on the pretreatment facility at the Hanford Site in Washington State. This facility was to separate nuclear waste into two streams for treatment in other site facilities. However, EM stopped design and construction of the facility in 2012 due to technical challenges. According to expenditure data, over half of the $752 million EM spent was for overhead, oversight, procurements, and facility maintenance. The rest was spent resolving the technical challenges. DOE's fiscal year 2020 budget request states that EM plans to continue “limited activities”—such as maintaining the existing facility and storing uninstalled equipment—while construction remains on hold.

After working to address pretreatment facility technical challenges since 2012, EM and its contractor consider these challenges—ranging from facility ventilation concerns to preventing explosions during waste treatment—to be conceptually resolved. However, EM has not yet designed, engineered, or tested solutions to the challenges. In addition, the Defense Nuclear Facilities Safety Board—an independent agency that provides analysis, advice, and recommendations regarding safety at DOE's defense nuclear facilities—does not consider the challenges resolved pending additional information and, in some cases, additional design and engineering work by EM.

To begin treating waste by 2023 as required, EM has been pursuing alternatives to the pretreatment facility. Since 2013, EM has spent over $400 million pursuing alternatives for low-activity waste pretreatment capabilities originally planned for the pretreatment facility. However, as GAO reported in May 2015, EM did not properly define a mission need statement or a life-cycle cost estimate prior to selecting its preferred alternative for treating low-activity waste, consistent with analysis of alternatives best practices and DOE policy, and GAO recommended EM revise its analysis. In April 2019, EM began an analysis of alternatives for treating high-level waste, which EM expects to be completed in September 2020. However, as of February 2020, EM had not yet defined a mission need for this new analysis of alternatives and did not have a life-cycle cost estimate for its baseline alternative. Without these, decision makers will not have the information they need to make the best decisions for pretreating high-level waste, and EM cannot assure decision makers that alternative approaches meet mission needs.

Figure: Status of Construction on the Pretreatment Facility, Part of the Waste Treatment and Immobilization Plant at the Department of Energy's Hanford Site in Washington State

Figure: Status of Construction on the Pretreatment Facility, Part of the Waste Treatment and Immobilization Plant at the Department of Energy's Hanford Site in Washington State

Why GAO Did This Study

The Hanford Site in Washington State contains large quantities of nuclear waste. EM has been building the Waste Treatment and Immobilization Plant—which consists of multiple facilities, including a key pretreatment facility—to treat a large portion of the nuclear waste at Hanford. Under way since 2000 and costing over $11 billion to date—$3.8 billion of that spent on the pretreatment facility—the plant has faced technical challenges, cost overruns, and schedule delays. In late 2012, work on the pretreatment facility stopped until technical challenges could be resolved. In 2018, the U.S. Army Corps of Engineers reported that at current annual funding levels, completing the pretreatment facility on time would not be possible.

Senate Report 116-48 accompanying the National Defense Authorization Act for fiscal year 2020 included a provision for GAO to review this project. This report examines (1) the cost of pretreatment efforts from fiscal year 2013 through fiscal year 2018, (2) the status of the technical challenges facing the pretreatment facility, and (3) the steps EM is taking to start treating waste by 2023 as required, among other things. GAO toured the facility, analyzed EM documents and expenditure data, and interviewed EM officials.

Recommendations

GAO is making two recommendations, including that DOE ensure that its analysis of alternatives for pretreatment of high-level waste include a mission need statement and a life-cycle cost estimate for the baseline alternative. DOE concurred in principle with both recommendations.

Recommendations for Executive Action

Agency Affected Recommendation Status
Department of Energy
Priority Rec.
The Secretary of Energy should direct the Assistant Secretary of Environmental Management to ensure that EM's final AOA for HLW pretreatment at the Hanford Site includes a definition of mission need and life-cycle cost estimates for the baseline or status quo alternative, as called for in the best practices for an AOA process we have identified and DOE guidance. (Recommendation 1)
Open
In January 2023, DOE released its AOA for HLW treatment. In April 2024, after years of holistic negotiations with the state of Washington, DOE announced an agreement that includes further exploration of alternatives for HLW treatment. The agreement is now out for public comment. We will review this agreement once it is finalized and assess whether the steps taken by DOE satisfy this recommendation.
Department of Energy The Secretary of Energy should direct the Assistant Secretary of Environmental Management to follow the steps outlined in GAO's risk-informed decision-making framework as EM makes decisions about the future of the pretreatment mission; in particular, engaging the Washington State Department of Ecology in the AOA process, communicating with them throughout the process, and providing them with transparent information about the rationale behind the final decision. (Recommendation 2)
Closed – Implemented
In January 2023, DOE released its AOA for HLW treatment. According to DOE and Ecology officials, DOE engaged Ecology in the AOA process by communicating with them throughout the process and providing them with transparent information about the alternatives analyzed.

Full Report

GAO Contacts

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

Analysis of alternativesCost estimatesCost overrunsNuclear wasteNuclear waste cleanupNuclear waste managementSchedule slippagesTechnical challengesWaste treatmentWaste treatment plant