Skip to main content

NASA Contractor Whistleblowers: Steps Taken to Implement Program but Improvements to Timeliness and Guidance Needed

GAO-18-262 Published: Mar 08, 2018. Publicly Released: Apr 09, 2018.
Jump To:

Fast Facts

NASA relies on contractor employees to fulfill its mission—and these employees are legally protected from reprisal, such as demotion or firing, for whistleblowing. But is the agency fulfilling its duty to investigate reprisal complaints from these employees in a timely manner?

Since 2008, NASA has not made a final determination of whether or not a reprisal occurred in the required 30-day time frame, nor has the agency evaluated its process for reviewing those complaints in a timely manner. We recommended that NASA take steps to ensure that it meets its 30-day time frame.

Timeline for NASA Administrator’s Response for 5 Investigated Reprisal Cases from 2008 through June 2017

Figure illustrating the NASA Administrator's time frame for reviewing 5 investigated reprisal cases.

Figure illustrating the NASA Administrator's time frame for reviewing 5 investigated reprisal cases.

Skip to Highlights

Highlights

What GAO Found

From 2008 through June 2017, National Aeronautics and Space Administration (NASA) contractor and grantee employees submitted 48 reprisal complaints such as alleged firing or demotion for reporting fraud, waste, or abuse within the government. NASA's Inspector General addressed all 48 complaints, completed investigations for 6 of those complaints, and forwarded investigation reports to the NASA Administrator, who is responsible for making a final determination of whether reprisal occurred. The Administrator determined that none of the complaints qualified for protection under the law.

Further, in 5 of the 6 cases forwarded by the OIG, the Administrator was required by statute to make a final determination of reprisal within 30 days. GAO found that the Administrator did not meet this required time frame for all 5 cases and had no documented response for one of them (see figure for all 5 cases). According to officials from NASA's Office of General Counsel, each case must be handled on a case by case basis to ensure due process and 30 days is insufficient time to issue an order of final determination of reprisal. However, in order to ensure that whistleblower reprisal complaints are handled within required timeframes, NASA would have to monitor and evaluate its processes for making final determinations of reprisal, but it has not yet taken this step. Consequently, NASA does not know what changes may be needed to ensure that it is meeting the statutory 30-day requirement.

Figure: Timeline for NASA Administrator's Response for 5 Investigated Reprisal Cases Subject to Statutory 30-Day Final Determination from 2008 through June 2017

Figure: Timeline for NASA Administrator's Response for 5 Investigated Reprisal Cases Subject to Statutory 30-Day Final Determination from 2008 through June 2017

NASA communicates whistleblower protections to contractors through inclusion of a required contract clause. For example, GAO found that almost all—98 percent—of contracts would be expected to include a whistleblower clause as required by statute. However, certain elements of NASA whistleblower protection guidance have contributed to a different understanding of reprisal protections among officials at headquarters, a NASA center, and the Inspector General. For example, a July 2014 procurement notice and contract clause language resulted in different interpretations about when the protections apply. Federal internal control standards require that an entity should communicate necessary quality information internally to meet the objectives of its mission. Without additional clarity in its guidance on when the protections apply, NASA centers and procurement officials will be at risk of inconsistent implementation of the law.

Why GAO Did This Study

NASA obligated over $18 billion in contracts and more than $1 billion in grants in fiscal year 2016, and it relies on a significant number of contractor and grantee employees to accomplish its work. These employees are legally protected from reprisal—such as demotion or firing—for whistleblowing.

GAO was asked to review NASA's whistleblower reprisal protections for contractor and grantee employees. This report addresses, among other things, the extent to which (1) NASA's Inspector General investigated contractor and grantee whistleblower reprisal complaints; (2) NASA's Administrator reviewed reprisal complaints in a timely manner; and (3) NASA communicated the applicable whistleblower reprisal protections to contractors. GAO reviewed NASA and its Inspector General's policies and guidance; reviewed a generalizable sample of 100 contracts from all NASA centers with contracts in fiscal year 2016; and interviewed relevant officials and contractors, grantees, and advocacy groups.

Recommendations

GAO is making three recommendations to NASA, including evaluating the process for reviewing reprisal complaints to ensure it is meeting the required timeframe and clarifying guidance on when protections apply to contractor employees. NASA agreed with the recommendations and plans to develop a documented process to ensure it reviews reprisal complaints in a timely manner and clarify guidance as appropriate, among other things.

Recommendations for Executive Action

Agency Affected Recommendation Status
National Aeronautics and Space Administration The Administrator should monitor, evaluate, and make appropriate corrective actions, such as a documented process, to ensure it reviews reprisal complaints in a timely manner. (Recommendation 1)
Closed – Implemented
In it's response to this report, NASA concurred with this recommendation. In July 2020, NASA provided guidance on the Administrator's process for reviewing reprisal complaints submitted by the NASA Inspector General that includes procedures and timelines to meet statutory requirements. GAO has determined this is sufficient to close the recommendation as implemented.
National Aeronautics and Space Administration The Administrator should review NASA's guidance or develop other guidance, including defining major modification, to clarify when whistleblower protections are conveyed. (Recommendation 2)
Closed – Implemented
In it's response to this report, NASA concurred with this recommendation. In September 2018, NASA developed guidance on when current contracts should be modified which states that contracting officers are directed to review all relevant, active contracts awarded prior to July 29, 2014 to ensure the whistleblower clause is included, and if it has not, that clause would be incorporated. GAO has determined this is sufficient to meet the requirements to implement this recommendation.
National Aeronautics and Space Administration The Administrator should communicate whistleblower protections to grantees and subgrantees and their employees. (Recommendation 3)
Closed – Implemented
In it's response to this report, NASA concurred with this recommendation and said the agency plans to update the NASA Grant and Cooperative Agreement Manual (GCAM) to communicate whistleblower protections to grantees and subgrantees. In March 2020, NASA updated the GCAM to reflect whistleblower protections for grantees and subgrantees, including mechanisms to report possible reprisal. GAO has determined that this addition is sufficient to close this recommendation.

Full Report

GAO Contacts

Shelby S. Oakley
Director
Contracting and National Security Acquisitions

Media Inquiries

Sarah Kaczmarek
Managing Director
Office of Public Affairs

Public Inquiries

Topics

ContractorsEmployee demotionsEmployeesFederal contractorsInternal controlsRequirements definitionWhistleblower protectionWhistleblowersTimelinessCriminal investigations