Skip to main content

DHS Financial Management: Improved Use of Best Practices Could Help Manage System Modernization Project Risks

GAO-17-803T Published: Sep 26, 2017. Publicly Released: Sep 26, 2017.
Jump To:
Skip to Highlights

Highlights

What GAO Found

The Department of Homeland Security's (DHS) TRIO project represents a key effort to address long-standing financial management system deficiencies. During 2012 and 2013, the TRIO components--U.S. Coast Guard (Coast Guard), Transportation Security Administration (TSA), and Domestic Nuclear Detection Office (DNDO)--each completed an alternatives analysis (AA) to determine a preferred alternative for modernizing its financial management system. GAO found that DNDO's AA substantially met the four characteristics--well-documented, comprehensive, unbiased, and credible--that GAO previously identified for a reliable, high-quality analysis of alternatives (AOA) process. However, Coast Guard's and TSA's AAs did not fully or substantially meet three of these characteristics, and DHS guidance for conducting AAs did not substantially incorporate certain best practices, such as identifying significant risks and mitigation strategies and performing an independent review to help validate the AOA process. Based on these analyses and other factors, the TRIO components determined that migrating to a federal shared service provider (SSP) represented the best alternative, and in 2014, DHS selected the Department of the Interior's Interior Business Center (IBC) as the federal SSP for the project. However, because Coast Guard's and TSA's AAs did not fully or substantially reflect all of the characteristics noted above, they are at increased risk that the alternative selected may not achieve mission needs.

DHS also did not fully follow best practices for managing project risks related to its use of IBC on the TRIO project. Specifically, DHS followed three of seven risk management best practices, such as determining risk sources and categories and establishing a risk management strategy. However, it did not fully follow four best practices for defining risk parameters, identifying risks, developing risk mitigation plans, and implementing these plans largely because its guidance did not sufficiently address these best practices. For example, although DHS created joint teams with IBC and provided additional resources to IBC to help address risk mitigation concerns, it did not always develop sufficiently detailed risk mitigation plans that also included contingency plans for selected critical risks. As a result, although IBC's capacity and experience for migrating large agencies the size of Coast Guard and TSA was identified as a risk in July 2014, a contingency plan working group to address this concern was not established until January 2017. By not fully following risk management best practices, DHS is at increased risk that potential problems may not be identified or properly mitigated.

DHS, IBC, Office of Management and Budget (OMB), and other federal oversight agencies identified various challenges that have impacted the TRIO project and contributed to a 2-year delay in the implementation of Coast Guard's and TSA's modernized solutions. These challenges include the lack of sufficient resources, aggressive schedule, complex requirements, increased costs, and project management and communication concerns. To help address these challenges, DHS and IBC established review teams and have taken other steps to assess potential mitigating steps. In May 2017, DHS determined that migrating the solution from IBC to a DHS data center represented the best option and initiated discovery efforts to further assess this as its path forward for the TRIO project.

Why GAO Did This Study

This testimony summarizes the information contained in GAO's September 2017 report, entitled DHS Financial Management: Better Use of Best Practices Could Help Manage System Modernization Project Risks (GAO-17-799).

For more information, contact Asif A. Khan at (202) 512-9869 or khana@gao.gov.

Full Report

GAO Contacts

Office of Public Affairs

Topics

Analysis of alternativesBest practicesCost and scheduleFinancial managementFinancial management systemsHomeland securityInternal controlsProject managementRisk managementSoftwareTechnology modernization programs